NEW FEATURES

APPLICATION ENHANCEMENTS

  • Implemented Versioned User Settings to improve User Experience when using multiple versions of the application.
  • Improved the performance of the Cash Flow Calculator.
  • Improved the performance of the Code Flow Calculator.
  • Improved the performance of the Code Set Allocations Calculator.
  • Improved how concurrent operations are scheduled to greatly improve the overall performance of multi-user environments.
  • Added the ability to remove multiple Codes at once instead of individually.
  • Changed the default Project Message level from Error to Warning for Mismatched Resource Usages project message.
  • Added the ability to apply colours to an entire row of the Project Analysis window.
  • Updated and Extended the Project Analysis report to include new information and be more consistent with the Analysis window.
  • Added Signature lines to Project Analysis Report.
  • Added the ability to show Provisional Sums, Risk and Opportunities, Pre-adjustments and Post-adjustments on the Project Analysis window and report.
  • Added column to Project Analysis window that shows each item as a percentage of it's parent.
  • Added the ability to set the Type/Category for Resources automatically created within a Quotation Comparison.
  • Display Zero Text Value on Submission Schedule and Spread Results if the line is Rate Only.
  • Added the ability to control the number of displayed decimal places in Global Defines.
  • Added the ability to update the Matrix Name using a Paste Cell action.
  • Added the ability to update the Matrix Cost Estimate Template using a Paste Cell action.
  • Added the ability to update the Matrix Attributes column values using a Paste Cell action.
  • Resource Explorer will show the value of Group Resources in the project when only Group Resources are selected.
  • User Defined Column Analysis now has the option to report on Resource User Defined Columns.
  • Add Unit column to Take Off Set Calculation sheet.
  • Added an additional formula called SumValueWithUnit to summarise Take Off Calculation sheet lines with a specified unit.
  • Allow server unit policies to manage Take Off units.
  • The Code column in Resource Explorer is now hidden by default.
  • Added a new field to DirectCostItemResponseModel and OverheadCostItemResponseModel in the API for IsTopLevelItem.
  • Added a new field to DirectCostItemResponseModel and OverheadCostItemResponseModel in the API for IsEffectivelyExcluded.
  • Added an alternative workflow for confirming a users membership in the local Administrators Group.
  • Added the ability to use double-click to navigate to Cost Estimates through the Code Allocation windows.
  • Updated the Project Lookup to show folders collapsed by default.
  • Added a summary of Item Allocation Results per Code to the Code Details Properties pane.
  • Added the ability to edit Cost Estimate line allocations through the Grid instead of only through the Properties Pane.
  • Added the ability to edit Resource Code Allocations through the Grid instead of just the Properties Pane.

BUG FIX

  • Resolved an issue where Quantities associated with new Spreading Rules could not be changed until the Project Properties window was saved.
  • Resolved an issue where the Expert Estimation Server service will fail to start if it exceeds the standard timeout duration.
  • Resolved an issue in the Direct and Overhead Code Allocations Properties Pane where the Add and Remove buttons were not being enabled.
  • Resolved an issue in the Code Set Calculation where Group Resources being influenced by a Percentage formula at a higher level were not being correctly accounted for.
  • Resolved an issue where only one Code Set would be automatically calculated when a project was imported.
  • Resolved an issue where using Previous and Next Cost Estimate actions could lead to a Client-side Deadlock.
  • Resolved an issue where incorrect information was being shown on the Spread Results Options pane.
  • Resolved an issue in the Spread Results Properties Pane where Summary line totals were included in the Summation values being shown.
  • Resolved an issue where changes to Colour Profiles were not being displayed until the application was closed and reopened.
  • Resolved an issue where accessing a project while it was being archived could leave the project in an unpredictable state.
  • Resolved an issue where opening the Save Dialog when exporting a report could cause an exception if the saved path was invalid.
  • Resolved an issue where an error may occur when updating Project details in the client-side cache.
  • Resolved an issue where the Getting Started overlay in the Cost Estimate would remain present after adding Cost Estimate lines.
  • Resolved an issue where users may receive an error in the Subcontractor Items window when User Defined values are updated.
  • Resolved an issue when multiple users opening/saving Saved Report Configurations could cause an exception.
  • Resolved an issue where certain invalid actions could be applied to a Self-Performed Subcontractor.
  • Resolved an issue where pre-import/export Drive Space checks were inconsistent.
  • Improved handling of Automatic Proportioning for Subcontractor and Quotation Comparisons for values close to 100%.
  • Improved the Resource, Matrix Item and Project lookup controls so that moving the mouse over the drop down list does not select an item.
  • Improved the loading speed of the Quotation Comparison Details report.
  • Added a prefix of OH to Overhead Items being printed in the Code Set Item Summary report when Cost Estimate lines are shown.
  • Fixed a number of reported and unreported bugs.