Currency Analysis Report

The Currency Analysis Report displays a per schedule item breakdown of the different currencies used in a project.

Currency Analysis Report

REPORT

The report displays the following information:

  • Line #
  • Item #
  • Description
  • Quantity
  • Unit
  • Estimated Rate
  • Estimated Total
  • Currency Total

FORMATTING OPTIONS

You can change the format of the data by clicking the Change button, in the bottom left-hand corner in the Options section of the report.

Currency Analysis Report - formatting options

FORMATTING OPTION

DESCRIPTION

Show Resource Types

If this option is checked, each currency will display the total value per Resource Type (Labour, Material, Plant, Subcontract and Other) for each item listed.

Displayed Currencies

The option that allows you to select the currencies that will be displayed within the Currency Analysis report.

The project base currency will automatically be selected and displayed on the report.

Note: General Report Options are available as standard for this report.