Cash Flow Scenario Options – Advanced/Deferred Costs
Genesis edition only.
The Advanced/Deferred Costs section of the Cash Flow Scenario Options provides you with the ability to include per-day cost amounts that contribute to a Cash Flow Scenario's lifetime. Advance/Deferred Costs can represent a mobilisation payment or a forward contingency for additional resources that are required for an activity.
To change the information in this section, click the Edit (
) button in the Cash Flow Options ribbon toolbar.
Note: Value added as an Advanced/Deferred Cost represents a lump sum to a Cash Flow scenario and does not relate to the overall Project or Resource Type Totals for a project.
Cash Flow Scenario Options window – Advanced/Deferred Costs
ADVANCED/DEFERRED COSTS
Clicking the Add button creates a new Advanced/Deferred Cost row within the window:
|
FIELD |
DESCRIPTION |
|---|---|
|
Cost Date |
Represents the unique Date in which a total value for an Advanced/Deferred Cost is incurred. |
|
Description |
The Description is an optional field and can provide additional information regarding the purpose of the Advanced/Deferred Cost added to the Cash Flow Scenario. |
|
Value |
The Value column represents the value of the Advanced/Deferred Cost. This value is either a positive (addition) or negative (deduction) to the cost of the Project for the selected Cash Flow Scenario. |
|
Cumulative Value |
The Cumulative Value displays the combined total for all Advanced or Deferred Costs applied to the Cash Flow Scenario up to the recorded Cost Date. For a balanced Cash Flow Scenario (a scenario that does not incur a deficit or surplus based on Advanced/Deferred Costs) the cumulative value on the final line should equate to zero so that the results are balanced. For ease of reference with larger lists of Advanced/Deferred Costs, a summary line is displayed below the table to display whether the Cash Flow Scenario is balanced or not. Note: This column is read-only. |